Monthly
Production Of
10 /20 kg Capacity laminated Jute Bag
Sewing
10 hours (Normal) 13
Sewing Machines x 2000
pieces/Per
Machine x26 days = 6,76,000 pieces
16 hours (Double Shift) 13 Sewing Machines x 3200 pieces/Per Machine x26 days
= 10,81,600 pieces
Lamination
10 Hours Lamination
Production Capacity 13,000 Yards
16 Hour Lamination Production Capacity 20,800 Yards
Printing
According To Sewing
Production Capacity
In 2 (two) shifts of 10 (Ten) hours & 16
(Sixteen) hours each, we are capable to produce 36,000 (thirty six thousand)
pcs. 10 /20 Kg. Capacity Laminated Jute bags per day. Calculating 26 (twenty
six) working days, our production capacity is 9,36,000 (nine lac thirty six thousand) pcs. per month
List
Of Equipment/machinery
1. Electric
Sewing Machine(Lock Stich) =13 Nos
2. Complete
Laminating Machine = 01 Nos
3. Bale
Press Machine = 01 Unit
4. Printing
Table/branding = 01
Set
5. Printing
Equipment = A lot
6. Others
Cutting Tools, Water Pumps, Deep Tubule E.t.c